Boiler Replacement & AHU Upgrades – Live Commercial Office, Central London
Service: Project Management & Building Surveying
Sector: Commercial Office
Location: Central London
The Challenge
We were appointed to manage the replacement of ageing boiler plant and the upgrade of Air Handling Units (AHUs) within a fully occupied multi-tenant office building.
The key constraint was clear: the building had to remain fully operational throughout the works. Any interruption to heating or ventilation would have directly impacted tenant business continuity.
Our Solution
We developed and implemented a phased delivery strategy, replacing systems in carefully planned sections rather than undertaking a full shutdown.
Our role included:
- Project scoping & methodology development – defining a practical, safe, and efficient approach to delivering works in a live environment
- Stakeholder coordination – acting as the central point of contact between managing agents, tenants, and the project team
- Tenant liaison – maintaining clear, proactive communication to minimise disruption
- Programme management – sequencing works to ensure continuity of services at all times
- Cost control – agreeing project costs, managing variations, and certifying completed works
- Progress reporting – issuing regular weekly updates to all stakeholders
Key Features
- Phased boiler and AHU replacement with zero full-building shutdown
- Continuous occupation maintained throughout
- Close coordination with managing agents and multiple tenants
- Live environment risk management and mitigation
- Central London logistics planning
The Outcome
The project was delivered successfully with no disruption to tenant operations, demonstrating the effectiveness of our phased approach and stakeholder management.
- ✔ Critical building services maintained at all times
- ✔ Works delivered to agreed cost and programme
- ✔ Improved system performance and energy efficiency
- ✔ Positive engagement from tenants and managing agents